37 changes: 33 additions & 4 deletions docs/gsd-method.md
Original file line number Diff line number Diff line change
@@ -1,4 +1,4 @@
# GSD method in Firstmate
# GSD method in Firstmate, revision 2

This document is Firstmate's adaptation of the GSD method from [open-gsd/gsd-core](https://github.com/open-gsd/gsd-core): the approach without the tool.
It is a running document: the rules above the log are the current contract, and the dated log at the bottom is the evidence that shaped them.
Expand Down Expand Up @@ -46,8 +46,10 @@ The mechanisms are referenced, not restated; their owners are `AGENTS.md` sectio
### 3.4 The Don't-Hand-Roll list

- Rule: research names the problems that must use an engine or library rather than custom code, and a plan that hand-rolls one of them fails plan-check.
- Mechanism: the plan-check brief carries the list as a mandatory dimension, and the ship brief for each execution task carries the entries that task touches.
- Artifact and owner: a `Don't Hand-Roll` section in the synthesis document, owned by the synthesizer and frozen by the captain's engine ruling.
- Rule: before a proof slice lands on local main, a code-level Don't-Hand-Roll audit and an independent critic must both pass, and their findings must never be deferred as residual work.
- Why: the Blockvalley Phase 1 retro found hand-rolled compositing and animation in a slice that had passed its earlier gates.
- Mechanism: the plan-check brief carries the list as a mandatory dimension, each ship brief carries the entries that task touches, and local-main landing requires both the code audit and critic verdict.
- Artifact and owner: the synthesis document owns the frozen `Don't Hand-Roll` list, while the independent critic's report owns the code-level verdict against it.

### 3.5 Prescriptive research output

Expand All @@ -63,6 +65,21 @@ The mechanisms are referenced, not restated; their owners are `AGENTS.md` sectio

## 4. The plan cycle and its hard cap

### 4.1 Phase-plan budget

- Rule: every plan starts with a one-page slice contract that sets numeric caps for execution tasks and acceptance criteria per task, and the full plan must stay within those caps.
- Rule: before CHECK, the synthesizer runs a deletion pass that removes every task, criterion, explanation, and executable surface not required by that slice contract.
- Why: the Blockvalley Phase 1 retro found that four rewrites grew the plan from 790 to 1,220 lines while it was nominally converging.

### 4.2 Scope-cut reconciliation gate

- Rule: every scope cut produces one signed scope-delta artifact whose authoritative rows are `kept`, `changed`, or `parked`, and no affected work continues until every live worker acknowledges its row.
- Why: the Blockvalley Phase 1 retro found live briefs still requesting work that a later scope cut had parked.
- Mechanism: the governing firstmate or secondmate tombstones superseded acceptance criteria, rewrites affected live briefs, records each worker acknowledgment, and blocks dispatch, execution, and landing until the matrix is reconciled.
- Artifact and owner: the governing firstmate or secondmate owns the signed scope-delta artifact as the single post-cut matrix, while the captain owns the ruling it records.

### 4.3 WRITE, CHECK, PATCH

- The cycle is WRITE once, CHECK once, PATCH once.
- WRITE: the synthesizer produces the phase plan from the research and the CONTEXT document.
- CHECK: one adversarial plan-check returns BLOCKER and WARNING findings with a concrete fix per finding.
Expand Down Expand Up @@ -104,15 +121,26 @@ This is the current setting as the captain set it on 2026-08-29; the captain's p
- The build hits the phase's named proof, for example "the slice on the captain's phone", without a re-plan.
- Fable spend per phase is at most one HIGH-effort Round 1 seat; zero is valid only under the captain-approved fallback in section 5.

### 7.1 Capture-coverage contract

- Rule: an "on the phone" proof passes only with a capture manifest that names every required element ID, the camera bounds, one deterministic state and frame, and an evidence link for every acceptance criterion.
- Why: the Blockvalley Phase 1 retro found that phone captures could look successful while omitting required elements and interactions.
- Artifact and owner: the proof-slice worker owns the capture manifest, and the independent critic verifies its criterion coverage before local-main landing.

## 8. How we review our use of it

- After each phase's named proof lands, the governing secondmate posts one keyed check-in as a usage retrospective: what the method caught, what it cost, and what this document got wrong.
- The parent firstmate folds accepted changes into the sections above and records the retrospective as a log entry below.
- The log is the record; it is evidence-backed, dated, and pruned rather than appended forever, under the same contract as `data/learnings.md`.

### 8.1 Check-in cost accounting

- Rule: every phase check-in records the model used, the number of rounds, and elapsed wall time, with unavailable values marked unknown rather than reconstructed later.
- Why: the Blockvalley Phase 1 retro could not recover complete worker, model, and wall-time totals after task cleanup.

## Log

Entries are dated, cite their evidence by path, and are rewritten or removed when superseded.
Entries are dated, cite their evidence by stable name or path, and are rewritten or removed when superseded.

- 2026-08-28 - Blockvalley Phase 0 ran the method by hand from a plan with a CONTEXT section, three researchers, and one synthesizer (`data/blockvalley-research-plan-phase0-2026-08-28.md`, `data/blockvalley-p0-synth-s/RESEARCH-0.md`, both in the Blockvalley home).
It caught the real failure: the earlier substitution program had assumed a renderer could be hand-rolled from repainted photos, and the research named y-sort, autotile, and shadows as Don't-Hand-Roll items with provenance.
Expand All @@ -125,3 +153,4 @@ Entries are dated, cite their evidence by path, and are rewritten or removed whe
Consequence recorded in section 4 and section 5: write once, check once, patch once on Codex, escalate on the third failure, Fable only at HIGH and only for Round 1.
- 2026-08-29 - The captain set the planning and model rules that sections 4 and 5 state, in the Blockvalley steering protocol (`data/steering-protocol.md`, "Planning and model rules"); the Phase 1 scope cut restated the plan-round cap and the slice-element rule for every task (`data/blockvalley-p1-scope-cut-2026-08-29.md`).
The captain's UX rulings file is the worked example of a CONTEXT document that bounds behaviour without ruling on looks (`data/blockvalley-ux-v1/UX-RULINGS-v1.md`).
- 2026-08-30 - The Blockvalley Phase 1 retro tightened revision 2 with a phase-plan budget, a scope-cut reconciliation gate, a pre-landing code-level Don't-Hand-Roll audit and independent critic, a capture-coverage contract, and minimal check-in cost accounting.