As discussed here:

#862 (comment)

the milestone #3 task is much greater than we originally envisioned. We need to reconcile changes to the substrate code base since we started and then merge our changes back into the main tree in order to propose an upstream PR and run the most up-to-date performance tests. So, I extended the time needed for this task to 6 months. Thank you.

Project Abstract

Please replace these instructions with a brief description of your project summarising key points (1-2 paragraphs).

If your application is a follow-up to a previous grant, please mention which one in the first line of the abstract and include a link to previous pull requests if applicable.

Grant level

  • Level 1: Up to $10,000, 2 approvals
  • Level 2: Up to $30,000, 3 approvals
  • Level 3: Unlimited, 5 approvals (for >$100k: Web3 Foundation Council approval)

Application Checklist

  • The application template has been copied and aptly renamed (project_name.md).
  • I have read the application guidelines.
  • A BTC, Ethereum (USDC/DAI) or Polkadot/Kusama (aUSD/USDT) address for the payment of the milestones is provided in the application.
  • The software delivered for this grant will be released under an open-source license specified in the application.
  • The initial PR contains only one commit (squash and force-push if needed).
  • The grant will only be announced once the first milestone has been accepted (see the announcement guidelines).
  • I prefer the discussion of this application to take place in a private Element/Matrix channel. My username is: @_______:matrix.org (change the homeserver if you use a different one)

As discussed here:

w3f#862 (comment)

the milestone w3f#3 task is much greater than we originally envisioned. We need to reconcile changes to the substrate code base since we started and then merge our changes back into the main tree in order to propose an upstream PR and run the most up-to-date performance tests. So, I extended the time needed for this task to 6 months. Thank you.
@CLAassistant
Copy link

CLAassistant commented Feb 20, 2023

CLA assistant check
All committers have signed the CLA.

Copy link
Member

@semuelle semuelle left a comment

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

Thanks for the update, @juntao.

@Noc2 Noc2 added the ready for review The project is ready to be reviewed by the committee members. label Feb 20, 2023
@Noc2 Noc2 merged commit 3caf045 into w3f:master Feb 20, 2023
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Labels

ready for review The project is ready to be reviewed by the committee members.

Projects

None yet

Development

Successfully merging this pull request may close these issues.

5 participants