This file contains bidirectional Unicode text that may be interpreted or compiled differently than what appears below. To review, open the file in an editor that reveals hidden Unicode characters.
Learn more about bidirectional Unicode characters
This file contains bidirectional Unicode text that may be interpreted or compiled differently than what appears below. To review, open the file in an editor that reveals hidden Unicode characters.
Learn more about bidirectional Unicode characters
This file contains bidirectional Unicode text that may be interpreted or compiled differently than what appears below. To review, open the file in an editor that reveals hidden Unicode characters.
Learn more about bidirectional Unicode characters
This file contains bidirectional Unicode text that may be interpreted or compiled differently than what appears below. To review, open the file in an editor that reveals hidden Unicode characters.
Learn more about bidirectional Unicode characters
Original file line number | Diff line number | Diff line change |
---|---|---|
@@ -1,7 +1,7 @@ | ||
CoST IDS element,CoST IDS draft definition,Mapping to OC for Infrastructure,Mapping from OCDS | ||
Variation to contract price,Difference between the price at contract award and the current projected price,"Contracting process: For each variation, publish an entry with a ``.date`` and ``.description`` in ``.summary.modifications`` with ``.type`` of 'value'. Provide the contract value before the variation in ``.oldContractValue`` and the contract value after the variation in ``.newContractValue``",Monitor ``contracts.value`` for changes. Copy ``contracts.amendments.description`` to ``.description`` and ``release.date`` to ``.date`` | ||
Escalation of contract price,"Escalation to date of the price of materials, labour, equipment etc. due to fluctuations in inflation, currency etc.","Contracting process: For each escalation, publish an entry with a ``.date`` and ``.description`` in ``.summary.modifications`` with ``.type`` of 'value'. Provide the contract value before the escalation in ``.oldContractValue`` and the contract value after the escalation in ``.newContractValue``",Monitor ``contracts.value`` for changes. Copy ``contracts.amendments.description`` to ``.description`` and ``release.date`` to ``.date`` | ||
Variation to contract duration,Difference between original duration at contract award and the current projected duration in weeks.,"Contracting process: For each variation, publish an entry with a ``.date`` and ``.description`` in ``.summary.modifications`` with ``.type`` of 'duration'. Provide the contract period before the variation in ``.oldContractPeriod`` and the contract period after the variation in ``.newContractPeriod``",Monitor ``contracts.period`` for changes. Copy ``contracts.amendments.description`` to ``.description`` and ``release.date`` to ``.date`` | ||
Variation to contract scope,Any changes between original scope at contract award and the current scope,"Contracting process: For each variation, publish an entry with a ``.date`` and ``.description`` in ``.summary.modifications`` with ``.type`` of 'scope'","Monitor ``contracts.description``, ``contracts.items`` and ``contracts.implementation.milestones`` for changes. Copy ``contracts.amendments.description`` to ``.description`` and ``release.date`` to ``.date``" | ||
Reasons for price changes,"Summary of reasons for primary changes (e.g. variations) that then lead to changes in contract price, major price fluctuations and accumulative increase or decrease in price.","Contracting process: For each variation, provide a ``.rationale`` in ``.summary.modifications``.",Copy ``contracts.amendments.rationale`` to ``.rationale`` | ||
Reasons for scope and duration changes,Summary of reasons for primary changes (e.g. variations) that then lead to changes in the scope and duration.,"Contracting process: For each variation, provide a ``.rationale`` in ``.summary.modifications``.",Copy ``contracts.amendments.rationale`` to ``.rationale`` | ||
CoST IDS element,CoST IDS draft definition,Mapping to OC4IDS,Mapping from OCDS | ||
Variation to contract price,Difference between the price at contract award and the current projected price,"Contracting process: For each variation, publish an entry with a ``.date`` and ``.description`` in ``.summary.modifications`` with ``.type`` of 'value'. Provide the contract value before the variation in ``.oldContractValue`` and the contract value after the variation in ``.newContractValue``",*Monitor* ``contracts.value`` *for changes. Copy* ``contracts.amendments.description`` *to* ``.description`` *and* ``release.date`` *to* ``.date``. | ||
Escalation of contract price,"Escalation to date of the price of materials, labour, equipment etc. due to fluctuations in inflation, currency etc.","Contracting process: For each escalation, publish an entry with a ``.date`` and ``.description`` in ``.summary.modifications`` with ``.type`` of 'value'. Provide the contract value before the escalation in ``.oldContractValue`` and the contract value after the escalation in ``.newContractValue``",*Monitor* ``contracts.value`` *for changes. Copy* ``contracts.amendments.description`` *to* ``.description`` *and* ``release.date`` *to* ``.date``. | ||
Variation to contract duration,Difference between original duration at contract award and the current projected duration in weeks.,"Contracting process: For each variation, publish an entry with a ``.date`` and ``.description`` in ``.summary.modifications`` with ``.type`` of 'duration'. Provide the contract period before the variation in ``.oldContractPeriod`` and the contract period after the variation in ``.newContractPeriod``",*Monitor* ``contracts.period`` *for changes. Copy* ``contracts.amendments.description`` *to* ``.description`` *and* ``release.date`` *to* ``.date``. | ||
Variation to contract scope,Any changes between original scope at contract award and the current scope,"Contracting process: For each variation, publish an entry with a ``.date`` and ``.description`` in ``.summary.modifications`` with ``.type`` of 'scope'","*Monitor* ``contracts.description``, ``contracts.items`` *and* ``contracts.implementation.milestones`` *for changes. Copy* ``contracts.amendments.description`` *to* ``.description`` *and* ``release.date`` *to* ``.date``." | ||
Reasons for price changes,"Summary of reasons for primary changes (e.g. variations) that then lead to changes in contract price, major price fluctuations and accumulative increase or decrease in price.","Contracting process: For each variation, provide a ``.rationale`` in ``.summary.modifications``.",*Copy* ``contracts.amendments.rationale`` *to* ``.rationale``. | ||
Reasons for scope and duration changes,Summary of reasons for primary changes (e.g. variations) that then lead to changes in the scope and duration.,"Contracting process: For each variation, provide a ``.rationale`` in ``.summary.modifications``.",*Copy* ``contracts.amendments.rationale`` *to* ``.rationale``. |