Original file line number Diff line number Diff line change
Expand Up @@ -92,7 +92,46 @@ us to validate that the upgrades work as expected in CI prior to deploying them
To run fork tests, run `just test-upgrade`. You will need to set `ETH_RPC_URL` to an archival mainnet node.

When multiple upgrades are in flight at the same time, the fork tests stack upgrades on top of one another. Since the
tip of `develop` must contain the implementation for the latest upgrade only, fork tests that run upgrades prior to
the latest one must use deployed instances of the OPCM. For example, as of this writing upgrades 13, 14, and 15 are
all in flight. Therefore, the fork tests will use deployed versions of the OPCM for upgrades 13 and 14 and whatever
is on `develop` for upgrade 15. See `OPContractsManager.t.sol` for the implementation of the fork tests.
tip of `develop` must contain the implementation for the latest upgrade only, fork tests that run upgrades prior to
the latest one must use deployed instances of the OPCM. For example, as of this writing upgrades 13, 14, and 15 are
all in flight. Therefore, the fork tests will use deployed versions of the OPCM for upgrades 13 and 14 and whatever
is on `develop` for upgrade 15. See `OPContractsManager.t.sol` for the implementation of the fork tests.

## Modifying Contracts for Upgrade

When making changes to a contract there are few situations to bear in mind.

### The contract's `initializer()` is updated

Typically a contract's `initializer()` will be modified when a new storage variable is added which
needs to be set. This may either be done by adding a new argument to the `initializer()`, by
reading a value from the environment, or by reading a value from another contract.

Whatever the case, a new `upgrade()` method should also be added which uses the same logic to set
the new storage variable.

In addition, the contract should inherit from `ReinitializableBase` and the `initializer()` and `upgrade()`
methods should have the `reinitializer(reinitVersion())` modifier.

The OPCM must then use `ProxyAdmin.upgradeAndCall()` to call the `upgrade()` method. Additionally, if the
input value is not read from the chain, then it will need to be passed in as input. This will
require a new field to be added to the `OpChainConfig` struct.

### New derivation path events are being added

If a contract emits events which have an impact on the derivation path of a chain (this most often
occurs when a new `UpdateType` is added to the `SystemConfig.ConfigUpdate()` event), the best
practice is to:

1. Not emit the new event in the `initialize()` method (and not add an `upgrade()` method)
1. Have the `op-node` default to some value for that config.
1. Add a setter function with appropriate auth checks for the new config value.

This pattern has a few benefits. It enables L1 contracts to be upgraded in advance of an L2 hardfork
which reads these events. Another benefit is that it avoids the need to provide the new config value
as an input to the `OpChainConfig`, thus helping to keep the interface of the OPCM stable.

### No new storage variables or derivation path events are added

In this case no changes are required to `initialize()`, no new `upgrade()` method is needed, and the