Task

Purpose

Manage and working with tasks.

Understanding the Task Portlet

task 1

With an open task selected, the portlet shows all informations of the task. You can rate or start a task. Also you can create a "permalink" for external tools such as Mantis. If you start a task, it will show in the portlet "My Tasks". Also the status changes to "in progress".

Rate a Task

task 1

Only open tasks can be rated. Rating means that you put the estimated time to the task. You can also change the milestone, artifact, priority, url and description.

Started Task

task 2

After starting a task you can add hours or finish the task.

Add Hours

task 2

You can add hours without finishing the task.

Finishing

task 2

You can finish the task and set the spending time for the task. After finishing, the task will be shown as "completed".