`gfs_cyc` is being replaced in global-workflow, so taking this opportunity to move cycle management from the verif script entirely. Cycle control will be moved to the workflow manager.
`$CDUMP` is no longer used as a proxy for `$RUN`, so instances of CDUMP are replaced.
WalterKolczynski-NOAA
added a commit
to WalterKolczynski-NOAA/global-workflow
that referenced
this pull request
Sep 17, 2024
To facilitate longer and more flexible GFS cadences, the `gfs_cyc` variable is replaced with a specified interval. Up front, this is reflected in a change in the arguments for setup_exp to: ``` --interval <n_hours> ``` Where `n_hours` is the interval (in hours) between gfs forecasts. `n_hours` must be a multiple of 6. If 0, no gfs will be run (only gdas; only valid for cycled mode). The default value is 6 (every cycle). In cycled mode, there is an additional argument to control which cycle will be the first gfs cycle: ``` ---sdate_gfs <YYYYMMDDHH> ``` The default if not provided is `--idate` + 6h (first full cycle). As part of this change, some of the validation of the dates has been added. `--edate` has also been made optional and defaults to `--idate` if not provided. During `config.base` template-filling, `INTERVAL_GFS` (renamed from `STEP_GFS`) is defined as `--interval` and `SDATE_GFS as `--sdate_gfs`. Some changes were necessary to the gfs verification (metp) job, as `gfs_cyc` was being used downstream by verif-global. That has been removed, and instead workflow will be responsible for only running metp on the correct cycles. This also removes "do nothing" metp tasks that exit immediately, because only the last GFS cycle in a day would actually process verification. Now, metp has its own cycledef and always runs at 18z, regardless of whether gfs is running at 18z or not. This is simplier than trying to determine the last gfs cycle of a day when it could change from day to day. To facilitate this change, support for the undocumented rocoto dependency tag `taskvalid` is added, as the metp task needs to know whether the cycle has a gfsarch task or not. metp will trigger on gfsarch completing (as before), or gdasarch completing if there is no gfsarch. metp tasks are no longer generated for forecast-only, as the pgbanl files (copied of the 1p00 pgbanl files) are not generated for f-o anyway. If metp is needed for f-o, additional work will be needed. Additionally, a couple EE2 issues with the metp job are resolved (even though it is not run in ops): - verif-global update replaced `$CDUMP` with `$RUN` - `$DATAROOT` is no longer redefined in the metp job Depends on NOAA-EMC/EMC_verif-global#137 Resolves NOAA-EMC#260 Refs NOAA-EMC#1299
8 tasks
DavidHuber-NOAA
requested changes
Sep 17, 2024
| export EDATE_GFS=${EDATE_GFS:-$EDATE} | ||
| export VDATE="${VDATE:-$(echo $($NDATE -${VRFYBACK_HRS} $CDATE) | cut -c1-8)}" | ||
|
|
||
| cyc2run="${cyc}" |
Collaborator
There was a problem hiding this comment.
This changes the way verif-global is run. I think this is OK since it is not going to be operational, but just noting that it will now run every GFS cycle instead of once per day.
Contributor
Author
There was a problem hiding this comment.
Workflow is only running it at 18z, so it will function similarly to before.
DavidHuber-NOAA
approved these changes
Sep 17, 2024
Collaborator
DavidHuber-NOAA
left a comment
There was a problem hiding this comment.
Changes look good. Approve pending global-workflow reviews and CI testing.
WalterKolczynski-NOAA
added a commit
to WalterKolczynski-NOAA/global-workflow
that referenced
this pull request
Sep 28, 2024
To facilitate longer and more flexible GFS cadences, the `gfs_cyc` variable is replaced with a specified interval. Up front, this is reflected in a change in the arguments for setup_exp to: ``` --interval <n_hours> ``` Where `n_hours` is the interval (in hours) between gfs forecasts. `n_hours` must be a multiple of 6. If 0, no gfs will be run (only gdas; only valid for cycled mode). The default value is 6 (every cycle). In cycled mode, there is an additional argument to control which cycle will be the first gfs cycle: ``` ---sdate_gfs <YYYYMMDDHH> ``` The default if not provided is `--idate` + 6h (first full cycle). As part of this change, some of the validation of the dates has been added. `--edate` has also been made optional and defaults to `--idate` if not provided. During `config.base` template-filling, `INTERVAL_GFS` (renamed from `STEP_GFS`) is defined as `--interval` and `SDATE_GFS as `--sdate_gfs`. Some changes were necessary to the gfs verification (metp) job, as `gfs_cyc` was being used downstream by verif-global. That has been removed, and instead workflow will be responsible for only running metp on the correct cycles. This also removes "do nothing" metp tasks that exit immediately, because only the last GFS cycle in a day would actually process verification. Now, metp has its own cycledef and always runs at 18z, regardless of whether gfs is running at 18z or not. This is simplier than trying to determine the last gfs cycle of a day when it could change from day to day. To facilitate this change, support for the undocumented rocoto dependency tag `taskvalid` is added, as the metp task needs to know whether the cycle has a gfsarch task or not. metp will trigger on gfsarch completing (as before), or gdasarch completing if there is no gfsarch. metp tasks are no longer generated for forecast-only, as the pgbanl files (copied of the 1p00 pgbanl files) are not generated for f-o anyway. If metp is needed for f-o, additional work will be needed. Additionally, a couple EE2 issues with the metp job are resolved (even though it is not run in ops): - verif-global update replaced `$CDUMP` with `$RUN` - `$DATAROOT` is no longer redefined in the metp job Depends on NOAA-EMC/EMC_verif-global#137 Resolves NOAA-EMC#260 Refs NOAA-EMC#1299
WalterKolczynski-NOAA
added a commit
to WalterKolczynski-NOAA/global-workflow
that referenced
this pull request
Oct 1, 2024
To facilitate longer and more flexible GFS cadences, the `gfs_cyc` variable is replaced with a specified interval. Up front, this is reflected in a change in the arguments for setup_exp to: ``` --interval <n_hours> ``` Where `n_hours` is the interval (in hours) between gfs forecasts. `n_hours` must be a multiple of 6. If 0, no gfs will be run (only gdas; only valid for cycled mode). The default value is 6 (every cycle). In cycled mode, there is an additional argument to control which cycle will be the first gfs cycle: ``` ---sdate_gfs <YYYYMMDDHH> ``` The default if not provided is `--idate` + 6h (first full cycle). As part of this change, some of the validation of the dates has been added. `--edate` has also been made optional and defaults to `--idate` if not provided. During `config.base` template-filling, `INTERVAL_GFS` (renamed from `STEP_GFS`) is defined as `--interval` and `SDATE_GFS as `--sdate_gfs`. Some changes were necessary to the gfs verification (metp) job, as `gfs_cyc` was being used downstream by verif-global. That has been removed, and instead workflow will be responsible for only running metp on the correct cycles. This also removes "do nothing" metp tasks that exit immediately, because only the last GFS cycle in a day would actually process verification. Now, metp has its own cycledef and always runs at 18z, regardless of whether gfs is running at 18z or not. This is simplier than trying to determine the last gfs cycle of a day when it could change from day to day. To facilitate this change, support for the undocumented rocoto dependency tag `taskvalid` is added, as the metp task needs to know whether the cycle has a gfsarch task or not. metp will trigger on gfsarch completing (as before), or gdasarch completing if there is no gfsarch. metp tasks are no longer generated for forecast-only, as the pgbanl files (copied of the 1p00 pgbanl files) are not generated for f-o anyway. If metp is needed for f-o, additional work will be needed. Additionally, a couple EE2 issues with the metp job are resolved (even though it is not run in ops): - verif-global update replaced `$CDUMP` with `$RUN` - `$DATAROOT` is no longer redefined in the metp job Depends on NOAA-EMC/EMC_verif-global#137 Resolves NOAA-EMC#260 Refs NOAA-EMC#1299
malloryprow
approved these changes
Oct 10, 2024
WalterKolczynski-NOAA
added a commit
to NOAA-EMC/global-workflow
that referenced
this pull request
Oct 22, 2024
# Description To facilitate longer and more flexible GFS cadences, the `gfs_cyc` variable is replaced with a specified interval. Up front, this is reflected in a change in the arguments for setup_exp to: ``` --interval <n_hours> ``` Where `n_hours` is the interval (in hours) between gfs forecasts. `n_hours` must be a multiple of 6. If 0, no gfs will be run (only gdas; only valid for cycled mode). The default value is 6 (every cycle). (This is a change from current behavior of 24.) In cycled mode, there is an additional argument to control which cycle will be the first gfs cycle: ``` --sdate_gfs <YYYYMMDDHH> ``` The default if not provided is `--idate` + 6h (first full cycle). This is the same as current behavior when `gfs_cyc` is 6, but may vary from current behavior for other cadences. As part of this change, some of the validation of the dates has been added. `--edate` has also been made optional and defaults to `--idate` if not provided. During `config.base` template-filling, `INTERVAL_GFS` (renamed from `STEP_GFS`) is defined as `--interval` and `SDATE_GFS as `--sdate_gfs`. Some changes were necessary to the gfs verification (metp) job, as `gfs_cyc` was being used downstream by verif-global. That has been removed, and instead workflow will be responsible for only running metp on the correct cycles. This also removes "do nothing" metp tasks that exit immediately, because only the last GFS cycle in a day would actually process verification. Now, metp has its own cycledef and will (a) always runs at 18z, regardless of whether gfs is running at 18z or not, if the interval is less than 24h; (b) use the same cycledef as gfs if the interval is 24h or greater. This is simpler than trying to determine the last gfs cycle of a day when it could change from day to day. To facilitate this change, support for the undocumented rocoto dependency tag `taskvalid` is added, as the metp task needs to know whether the cycle has a gfsarch task or not. metp will trigger on gfsarch completing (as before), or look backwards for the last gfsarch to exist. Additionally, a couple EE2 issues with the metp job are resolved (even though it is not run in ops): - verif-global update replaced `$CDUMP` with `$RUN` - `$DATAROOT` is no longer redefined in the metp job Also corrects some dependency issues with the extractvars job for replay and the replay CI test. Depends on NOAA-EMC/EMC_verif-global#137 Resolves #260 Refs #1299 --------- Co-authored-by: David Huber <david.huber@noaa.gov>
EricSinsky-NOAA
pushed a commit
to EricSinsky-NOAA/global-workflow
that referenced
this pull request
Oct 24, 2024
To facilitate longer and more flexible GFS cadences, the `gfs_cyc` variable is replaced with a specified interval. Up front, this is reflected in a change in the arguments for setup_exp to: ``` --interval <n_hours> ``` Where `n_hours` is the interval (in hours) between gfs forecasts. `n_hours` must be a multiple of 6. If 0, no gfs will be run (only gdas; only valid for cycled mode). The default value is 6 (every cycle). (This is a change from current behavior of 24.) In cycled mode, there is an additional argument to control which cycle will be the first gfs cycle: ``` --sdate_gfs <YYYYMMDDHH> ``` The default if not provided is `--idate` + 6h (first full cycle). This is the same as current behavior when `gfs_cyc` is 6, but may vary from current behavior for other cadences. As part of this change, some of the validation of the dates has been added. `--edate` has also been made optional and defaults to `--idate` if not provided. During `config.base` template-filling, `INTERVAL_GFS` (renamed from `STEP_GFS`) is defined as `--interval` and `SDATE_GFS as `--sdate_gfs`. Some changes were necessary to the gfs verification (metp) job, as `gfs_cyc` was being used downstream by verif-global. That has been removed, and instead workflow will be responsible for only running metp on the correct cycles. This also removes "do nothing" metp tasks that exit immediately, because only the last GFS cycle in a day would actually process verification. Now, metp has its own cycledef and will (a) always runs at 18z, regardless of whether gfs is running at 18z or not, if the interval is less than 24h; (b) use the same cycledef as gfs if the interval is 24h or greater. This is simpler than trying to determine the last gfs cycle of a day when it could change from day to day. To facilitate this change, support for the undocumented rocoto dependency tag `taskvalid` is added, as the metp task needs to know whether the cycle has a gfsarch task or not. metp will trigger on gfsarch completing (as before), or look backwards for the last gfsarch to exist. Additionally, a couple EE2 issues with the metp job are resolved (even though it is not run in ops): - verif-global update replaced `$CDUMP` with `$RUN` - `$DATAROOT` is no longer redefined in the metp job Also corrects some dependency issues with the extractvars job for replay and the replay CI test. Depends on NOAA-EMC/EMC_verif-global#137 Resolves NOAA-EMC#260 Refs NOAA-EMC#1299 --------- Co-authored-by: David Huber <david.huber@noaa.gov>
This file contains hidden or bidirectional Unicode text that may be interpreted or compiled differently than what appears below. To review, open the file in an editor that reveals hidden Unicode characters.
Learn more about bidirectional Unicode characters
Sign up for free
to join this conversation on GitHub.
Already have an account?
Sign in to comment
Add this suggestion to a batch that can be applied as a single commit.This suggestion is invalid because no changes were made to the code.Suggestions cannot be applied while the pull request is closed.Suggestions cannot be applied while viewing a subset of changes.Only one suggestion per line can be applied in a batch.Add this suggestion to a batch that can be applied as a single commit.Applying suggestions on deleted lines is not supported.You must change the existing code in this line in order to create a valid suggestion.Outdated suggestions cannot be applied.This suggestion has been applied or marked resolved.Suggestions cannot be applied from pending reviews.Suggestions cannot be applied on multi-line comments.Suggestions cannot be applied while the pull request is queued to merge.Suggestion cannot be applied right now. Please check back later.
The dependency on gfs_cyc is removed from the global verif script. gfs_cyc is being replaced by an interval and running on the appropriate cycles will be handled by the workflow from hereon. Workflow will always run verif at 18z, regardless of if the GFS forecast is produced for that cycle.
Additionally, the deprecated
$CDUMPis replaced with the preferred$RUN.Refs: NOAA-EMC/global-workflow#2928